but where can I see the total cost of all tasks of a project?
run the report: "Cash flow on tasks" or "Cash flow on Resources" to get the total amount!
04-01-2008, 10:09 AM
Thanks for your answer. Wouldn't it be a good idea, to add a new column 'Total Cost' on the projects page, so that I don't need to run a report every time I want to know about the total cost?
Regards
Guido
Regards
Guido
04-01-2008, 10:34 AM
Hi Guido,
gklapper Wrote:
Wouldn't it be a good idea, to add a new column 'Total Cost' on the projects page, so that I don't need to run a report every time I want to know about the total cost?
couldn't agree more :-)