Is-it possible to change the "Predecessors" directly in the Gantt Chart view instead of in the "Task property" box?
I did not find the way to include a "Predecessors" column in the Gantt Chart.

Thanks,

JP
Hello,
unfortunatelly it is impossible to do what you want.

Anna

JP Tellier Wrote:
Is-it possible to change the "Predecessors" directly in the Gantt Chart view instead of in the "Task property" box?
I did not find the way to include a "Predecessors" column in the Gantt Chart.

Thanks,

JP


Actually if you select the two task that are linked and hit ctrl+shift+l this will unlink the two tasks then you can relink your task to you desired task with crtl+l. From what I've seen a link is the same as setting a predecessor.

hope this helps!