Hi,

I'm trying to move a task in Gant Chart but it won't let me move it to start on a weekend. I've tried modifying both the working time and the workspace properties but each time I apply them, the task refuses to start on the weekend date. When I go back to changing the working time (changing working time), it doesn't apply the changes to the days I select as non-default etc..

help...!:icon_frown:
Hi matthew,

matthewsmith Wrote:I'm trying to move a task in Gant Chart but it won't let me move it to start on a weekend. I've tried modifying both the working time and the workspace properties but each time I apply them, the task refuses to start on the weekend date.

as I remember, you are running ConceptDraw Project 2.x. Since I run the newest version on mac (3.4), I only can say how it is running in this version:
[Image: weekend.jpg]

I started a new project with no free days on the weekend:
[Image: weekend1.jpg]

So the problem does not apply with 3.4.
Hi Gerhard,

I created a new project with no free days on the weekend. Then I copied and pasted in my old project and it worked well. You are quite correct - you need to start the project off with a calendar set to normal working days all the way through.

Thank you very much for solving this for me.:)
Hi Matthew,

matthewsmith Wrote:You are quite correct - you need to start the project off with a calendar set to normal working days all the way through.

but I still don't like the idea ;-)

Good to be of service. Have fun with ConceptDraw Project!
Hello Gerhard and Matthew,

matthewsmith Wrote:You are quite correct - you need to start the project off with a calendar set to normal working days all the way through.
Gerhard Trimpin Wrote:but I still don't like the idea ;-)

Its great that you mentioned this one for we are going to change this one.
Do you have any propositions at this point so that it would be convenient for all users?

Thanks!
Hi Natalya,

Natalie Wrote:Do you have any propositions at this point so that it would be convenient for all users?

If you could allow with jump from field to field inside the workspace calendar - the same as in the calendar of the preferences!

Have a nice day!
Gerhard, do you mean making the jump from every date to date (1,2,3,4,5.....)?
Hi Nataly,

Natalie Wrote:Gerhard, do you mean making the jump from every date to date (1,2,3,4,5.....)?

no, if I have to change the working hours of a day and change the first time, I wish to jump to the next entry by . This is realised in the calendar of the preferences!