07-12-2007, 11:39 AM
I'm using version 3.4 on WinXp. I obtained my copy from Giveaway of the Day (thank you!). I am learning Concept Project and will use the program to manage our installation projects. These are like small construction (building) projects.
One of our projects has an a delayed start date (from 12 July 2007 to 23 July 2007). I looked in the manual, and have changed the date in the "Project" page (View>Projects). It also changes in the "Project" floating dialog, but it does not change in the Gantt chart.
I have no Deadlines, and 2 Milestones. Removing the Milestones did not fix it.
Am I making a mistake?
I have some small screenshots to demonstrate the changes, but have not been able to add these as Attachments.
One of our projects has an a delayed start date (from 12 July 2007 to 23 July 2007). I looked in the manual, and have changed the date in the "Project" page (View>Projects). It also changes in the "Project" floating dialog, but it does not change in the Gantt chart.
I have no Deadlines, and 2 Milestones. Removing the Milestones did not fix it.
Am I making a mistake?
I have some small screenshots to demonstrate the changes, but have not been able to add these as Attachments.
![[Image: project-moving.jpg]](http://www.trimpin.de/bilder/2007-07-19_cdp/project-moving.jpg)