Renee Wrote:
Can I change weekend dates for the application? I work on weekends and would like to see the progress in my Project!
You can make the weekends for the working days in your Project. In order to do it
follow the next instructions:
1. Change the working days in menu: Workspace\Workspace properties\Default calendar
Tick Saturday and Sunday. Click OK.
(Here you also can change working hours)
2. Then, in menu: Workspace\Change Working Time select all the days in the calendar and Set them as Default. Click OK.
It should help:^)
12-25-2006, 05:33 PM
Hi Natalie! Thanks for that! But…
Changing the weekends works only for one month. I have a project that last 2 years. Do I have to repeat the operation 24 times?
Changing the weekends works only for one month. I have a project that last 2 years. Do I have to repeat the operation 24 times?
12-26-2006, 05:30 PM
select all the days (not dates) in the calendar
It will change the default days for the whole project
It will change the default days for the whole project